Starling Manufacturing has developed the following standards for one of its products.
SIANDARD VARIABLE COSI CARDOne Unit of Product Materials: 5 metres ×$6 per metre Direct labour: 2 hours ×$8 per hour Variable manufacturing overhead: 2 hours ×$5 per hour Total standard variable cost per unit $30.0016.0010.00$56.00
The company records materials price variances at the time of purchase.
The following activity accured during the month of December:
Materials purchased: Materials used: Units produced: Direct labour: 5,200 metres costing $29,9004,750 metres 1,000 urits 2,100 hours costing $17,850
a.Calculate the direct materials price variance.
b.Calculate the direct materials usage variance.
c.Calculate the direct labour rate variance.
d.Calculate the direct labour efficiency variance.