Heft Company Produces a and B with Contribution Margins Per

question 85

Multiple Choice

Heft Company produces A and B with contribution margins per unit of $40 and $30, respectively. Only 500 labour hours and 300 machine hours are available for production.
Time requirements to produce one unit of A and B are as follows:
 Product A  Praduct B  Labour hours per unit 52 Machine hours per unit 14\begin{array} { l c c c } & \text { Product A } & \text { Praduct B } \\\text { Labour hours per unit }& 5 & 2 \\\text { Machine hours per unit } & 1 & 4\end{array}
-Refer to the figure.What is the constraint on machine hours for Heft Company?


Definitions:

Automobile Emissions

Pollutants released into the atmosphere by motor vehicles, contributing to air pollution and greenhouse gas concentrations.

Non-Renewable Fossil Fuels

Natural resources such as coal, oil, and natural gas that cannot be replenished within a human lifespan.

Industrial-Medical Revolution

A significant transformation in industry and medicine, often characterized by technological advancements and improved health care.

Related Questions