Lagory Co Started a Contract in June 2011 to Build a a Bridge

question 14

Multiple Choice

Lagory Co. started a contract in June 2011 to build a bridge at a fixed price of $14 million. The bridge was to be completed by October 2013. Total cumulative costs incurred by the end of December 2011 and 2012 were $2 million and $6 million, respectively. Lagory Co. is unable to estimate the total costs of the project prior to completion. Final costs at the end of the project totalled $11 million. How much revenue will Lagory Co. report in 2012?


Definitions:

Legally Binding Contract

A contract that is enforceable by law, meaning all parties involved must fulfill their obligations as agreed.

Panel Interviews

A type of interview where the candidate is questioned by multiple interviewers at the same time, often used in job selection processes.

Perform Under Pressure

The ability to function effectively in stressful or challenging situations without compromising performance.

Declining A Job Offer

The action of refusing a job proposal politely and professionally, often after considering various aspects of the offer.

Related Questions