Use the chart provided below to determine the impact if a company forgets to include $3,500 of inventory that was shipped FOB shipping point on December 25, 2013 but was still in transit at year end. The purchase invoice was processed in fiscal 2014.
Use the chart provided below to determine the impact if a company forgets to include $3,500 of inventory that was shipped FOB shipping point on December 25, 2013 but was still in transit at year end. The purchase invoice was processed in fiscal 2014.


Definitions:

Critical Path Method

A project management technique used to schedule project activities by identifying the longest sequence of dependent tasks.

Gantt Chart

A graphical display of the scheduling of tasks required to complete a project.

One-Time Events

Occurrences or activities that happen once and are not repeated, often unique or significant in nature.

Defined Time Period

A set duration, clearly specified, within which activities, processes, or events are to be initiated and completed.