Examlex

Solved

Archetype Fabrication Makes Pre-Stressed Concrete Forms for the Building Industry

question 159

Multiple Choice

Archetype Fabrication makes pre-stressed concrete forms for the building industry. They use just-in-time production and accounting methodology. At the beginning of January, selected account balances are shown in the T-accounts below. Archetype Fabrication makes pre-stressed concrete forms for the building industry. They use just-in-time production and accounting methodology. At the beginning of January, selected account balances are shown in the T-accounts below.   During January, the following 5 transactions take place: 1)  Purchase $40,000 of materials on account. 2)  Pay out $25,000 of direct labor costs. 3)  Incur $9,000 of manufacturing overhead costs. 4)  Complete 12 units. Each unit includes $1,500 of materials, $300 of direct labor, and $150 of manufacturing overhead costs. 5)  Sell 10 of the 12 completed units at a price of $2,200. - Use the T-accounts shown above to record the transactions, and then answer the following question: After transaction number 5, what was the balance in the Raw and in-process inventory account? A)  $25,400 B)  $36,600 C)  $22,000 D)  $24,000 During January, the following 5 transactions take place:
1) Purchase $40,000 of materials on account.
2) Pay out $25,000 of direct labor costs.
3) Incur $9,000 of manufacturing overhead costs.
4) Complete 12 units. Each unit includes $1,500 of materials, $300 of direct labor, and $150 of manufacturing overhead costs.
5) Sell 10 of the 12 completed units at a price of $2,200.
-
Use the T-accounts shown above to record the transactions, and then answer the following question:
After transaction number 5, what was the balance in the Raw and in-process inventory account?


Definitions:

Optimistic Time

The “best” activity completion time that could be obtained in a PERT network.

Probable Time

An estimate of the amount of time that might reasonably be expected to be needed to complete a specific task or project.

Expected Activity Time

In project management, it's the best estimate of the time required to complete a task, considering various factors like resources and complications.

PERT Analysis

Program Evaluation and Review Technique (PERT) analysis is a project management tool used to plan, schedule, and control complex activities, focusing on task durations to identify minimum project duration.

Related Questions