A branch of the U.S. Treasury Department, called the ________, administers the federal tax system.


Definitions:

Project Quality

The degree to which a project meets the requirements, standards, and objectives laid out for it.

Forward Pass

A process that identifies all the early start and early finish times.

Backward Pass

A process that identifies all the late start and late finish times.

Critical Path

In project management, the sequence of stages determining the minimum time to complete a project.