The NPV Rule Is Preferred to the Discounted Payback Period

question 90

Multiple Choice

The NPV rule is preferred to the discounted payback period as a project evaluation criterion because the discounted payback period rule ignores:
I.The initial cost
II.The timing of cash flows prior to the discounted payback period
III.Any cash flows beyond the discounted payback period