The following four steps are necessary in order to use an activity-based costing system:
1) Compute the allocation rate for each activity.
2) Identify activities and estimate their total costs.
3) Identify the cost driver for each activity and then estimate the quantity of each driver's allocation base.
4) Allocate the indirect costs to the cost object.
In what order are these steps performed?


Definitions:

Technological Change

Innovations in the way goods or services are produced, delivered, or utilized, often leading to efficiency gains or new capabilities.

Absenteeism

Refers to the consistent absence of an employee from their job without a valid reason, which can impact productivity and morale.

Team Viability

Refers to a team’s capacity for sustained success and maintaining effective performance over time.

Member Satisfaction

The degree to which the expectations and needs of a member of a group or organization are fulfilled.

Related Questions