Precedence Diagram Method

A project management tool that uses a graphical representation to depict project activities in a sequential order, highlighting dependencies.

Predecessor-successor Relationships

In project management, these relationships define the sequential order of tasks, where one task must be completed before the next one can start.

Forward Pass

A technique used in project management that involves calculating the earliest start and finish times for each task in a project schedule.

Crashing

An approach in project management to shorten the project schedule by adding resources to critical tasks.