Given the earliest and latest finish times for each of these activities, what are the activity lengths?
 Activity  EF  LF  Predecessors  A 33 B 1010 A  C 513 A  D 1818 B  E 1518 B  F 1119 C  G 819 C  H 2323 D, E  I 1523 F, G  J 2424 H, I \begin{array} { | c | c | c | c | } \hline \text { Activity } & \text { EF } & \text { LF } & \text { Predecessors } \\\hline \text { A } & 3 & 3 & \cdots \\\hline \text { B } & 10 & 10 & \text { A } \\\hline \text { C } & 5 & 13 & \text { A } \\\hline \text { D } & 18 & 18 & \text { B } \\\hline \text { E } & 15 & 18 & \text { B } \\\hline \text { F } & 11 & 19 & \text { C } \\\hline \text { G } & 8 & 19 & \text { C } \\\hline \text { H } & 23 & 23 & \text { D, E } \\\hline \text { I } & 15 & 23 & \text { F, G } \\\hline \text { J } & 24 & 24 & \text { H, I } \\\hline\end{array}


Definitions:

Canadian Dollars

The official currency of Canada, represented by the symbol CAD.

Trading Securities

Financial instruments like stocks or bonds held by a firm, primarily for the purpose of selling them in the near term to realize a gain.

Long-term

Pertaining to or occurring over an extended period, often exceeding one year, in the context of investments, loans, or planning.

Profit Margin

A financial ratio that measures the percentage of revenue remaining after all expenses have been deducted from sales.

Related Questions