Multiple Choice

What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days? What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?   A) 35 B) 36 C) 40 D) 41