Given the earliest and latest finish times for each of these activities, what are the activity lengths?
 Activity  EF  LF  Predecessors  A 33 B 1010 A  C 513 A  D 1818 B  E 1518 B  F 1119 C  G 819 C  H 2323 D, E  I 1523 F, G  J 2424 H, I \begin{array} { | c | c | c | c | } \hline \text { Activity } & \text { EF } & \text { LF } & \text { Predecessors } \\\hline \text { A } & 3 & 3 & \cdots \\\hline \text { B } & 10 & 10 & \text { A } \\\hline \text { C } & 5 & 13 & \text { A } \\\hline \text { D } & 18 & 18 & \text { B } \\\hline \text { E } & 15 & 18 & \text { B } \\\hline \text { F } & 11 & 19 & \text { C } \\\hline \text { G } & 8 & 19 & \text { C } \\\hline \text { H } & 23 & 23 & \text { D, E } \\\hline \text { I } & 15 & 23 & \text { F, G } \\\hline \text { J } & 24 & 24 & \text { H, I } \\\hline\end{array}


Definitions:

Express Contract

A legally binding agreement where the terms are stated clearly by the parties involved, either orally or in writing.

Disclosure

The act of making previously private or confidential information known to others.

General Public

The broad group of people in society who do not have a specific interest in particular topics or areas but are affected by or interested in general issues.

Organization Interests

The goals, priorities, and objectives that are pursued by an organization to ensure its growth, sustainability, and success.

Related Questions