Use the following information to solve the following questions:
On March 1, 2020, Mauritania Ltd. purchased land for $ 270,000 cash, which they intend to use for their new head office. Construction on the office building began on March 1. The following expenditures were incurred for construction:
 Date  Expenditures  March 1,2020$450,000 April 1,2020252,000 May 1,2020450,000 June 1,2020720,000\begin{array} { l l } \text { Date } & \text { Expenditures } \\\text { March } 1,2020 &\$450,000\\\text { April } 1,2020 & \mathbf { 2 5 2 , 0 0 0 } \\\text { May } 1,2020 & 450,000 \\\text { June } 1,2020 & 720,000\end{array} The office building was completed and ready for occupancy on July 1. To help pay for construction, Mauritania borrowed $ 360,000 on March 1, 2020, on a 9%, three-year note payable. Other than this note, the only other debt outstanding during 2020 was a $ 150,000, 10%, six-year note payable dated January 1, 2019.
-The weighted-average accumulated expenditures on the construction project during 2020 were


Definitions:

Related Questions