Queensbridge Corp. started a contract in June 2020 to build a bridge at a fixed price of $45 million. The bridge was to be completed by October 2022 at a total estimated cost of $35 million. Total cumulative costs incurred by the end of December 2020 and 2021 were $7 million and $24 million, respectively. Because of cost overruns in 2021, it is now expected that the project will cost $5,000,000 more than originally estimated. Final costs at the end of the project totaled $36 million. Queensbridge Corp. follows the guidance in IFRS.
Required:
Determine the amount of gross profit to be recognized for the years ended December 31, 2020 and December 31, 2021.
Migration patterns
The trends or movements of groups of people or animals from one location to another, often studied to understand reasons behind the movements and implications for both origin and destination areas.
Sanitation systems
Infrastructure and services designed to efficiently collect, treat, and dispose of human waste and wastewater to protect human health and the environment.
Nutritious food
Nutritious food refers to edibles that provide essential nutrients needed by the body for growth, maintenance, and proper functioning, including vitamins, minerals, proteins, and healthy fats.
Q12: The publisher of TV Weekly received
Q18: Apartment King (AK)is building a luxury
Q19: Cash flows from operations<br>A)is equivalent to cash
Q21: Discuss some of the conceptual framework concepts
Q27: Which statement is correct about an at
Q55: Which statement is not correct about "control"?<br>A)Control
Q55: JP Corporation had net income of $1,000,000
Q80: According to the above table.Amacon, whose year-end
Q107: Which statement is correct about joint arrangements?<br>A)IFRS
Q116: The analysis of a firm's profitability includes