Tyco Ltd entered into a contract to build a sports arena for $1,800,000. Construction commenced on August 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below: 202020212022 Costs incurred during the year 400,000500,000650,000 Estimated costs to complete at year end 1,200,000600,0000 Billings during the year 560,000640,000700,000 Cash collections during the year 500,000310,000990,000\begin{array} { | l | r | r | r | } \hline & \mathbf { 2 0 2 0 } & \mathbf { 2 0 2 1 } & \mathbf { 2 0 2 2 } \\\hline \text { Costs incurred during the year } & 400,000 & 500,000 & 650,000 \\\hline \text { Estimated costs to complete at year end } & 1,200,000 & 600,000 & 0 \\\hline \text { Billings during the year } & 560,000 & 640,000 & 700,000 \\\hline \text { Cash collections during the year } & 500,000 & 310,000 & 990,000 \\\hline\end{array} How much would the balance in accounts receivable be on the balance sheet of Tyco at the end of 2020 if Tyco uses the percentage of completion method?


Definitions:

Reneging

The act of going back on a promise, obligation, or deal.

Probability

An indicator of how likely it is that an event will happen, represented as a number ranging from 0 to 1.

System

A set of interrelated components that work together to achieve a common goal or perform a specific function.

Average Number

The arithmetic mean or central value of a set of numbers, calculated by dividing the sum of the values in the set by the number of values.

Related Questions