Use the information below to answer the following questions:
On 1 January 2010, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
$ 31 December 2010 $15000000 31 December 2011 $20000000 31 December 2012 $29000000\begin{array} { r r } & \$ \\\text { 31 December 2010 } & \$ 15000000 \\\text { 31 December 2011 } & \$ 20000000 \\\text { 31 December 2012 } & \$ 29000000\end{array}
Estimated costs were $50 000 000. The project was 35% complete at the end of 2010, 75% complete at the end of 2011, and 100% complete at the end of 2012. Revenues and costs were as estimated.
-What profit was earned during 2011 if the percentage of completion method was used?


Definitions:

Development Level

The stage or degree of growth, advancement, or maturity that an individual, group, or entity has achieved.

Leadership Style

A pattern of behaviors that leaders use to influence others, including how they make decisions, communicate, and motivate team members.

Fostering Confidence

The process of encouraging and building belief in one's abilities or potential in others.

Taxpayer

An individual or entity that is obligated to make payments to governmental authorities based on income earned or goods and services provided.

Related Questions