Custom Tile Works budgeted 2.5 hours of direct labour per unit at $12.20 per hour to produce 520 hand-painted mosaic tiles. The 520 tiles were completed using 1,400 hours of direct labour at $12.50 per hour. What is the direct labour price variance?