Refer to the PERT Diagram Below,where the Numbers Next to the Arrows

question 13

Multiple Choice

Refer to the PERT diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path? Refer to the PERT diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path?   A) A-B-D-F B) A-C-E-F C) A-B-D-E-F D) A-C-B-D-F E) A-C-B-D-E-F