Answer the Following Questions Using the Information Below

question 108

Multiple Choice

Answer the following questions using the information below:
A manufacturing firm is able to produce 2,000 pairs of sneakers per hour, at maximum efficiency. There are three eight-hour shifts each day. Due to unavoidable operating interruptions, production averages 1,600 units per hour. The plant actually operates only 27 days per month.
-What is the theoretical capacity for the month of April?


Definitions:

Chassis Electrical System

The network of electrical components and wiring that provides power and function to a vehicle's operational systems.

Power Distribution Module

A component in a vehicle or system that manages the distribution and regulation of electrical power to various parts.

Batteries

Electrochemical cells that store energy and release it in the form of electricity, used as a power source in many electronic devices and vehicles.

SAE Relay

A relay standardized by the Society of Automotive Engineers, designed for automotive electrical applications.

Related Questions