Write a cost estimating equation for each of the following conditions. Use y for estimated costs and X for activity of the cost driver. a. Direct manufacturing labour is $20 per hour.
B) Direct materials cost $8.00 per cubic metre.
C) Utilities have a minimum charge of $2,000 plus a charge of $0.05 per kilowatt hour.
D) Factory supplies average $10 per day plus $1.00 for each machine-hour per day.
E) Total manufacturing amortization includes $5,000 for straight-line plant amortization plus machinery amortization of $100 for each day operated.


Definitions:

Hedonic Treadmill

The hedonic treadmill is a theory suggesting that people consistently return to a relatively stable level of happiness despite major positive or negative events or life changes.

Richard Easterlin

An economist known for the Easterlin Paradox, which posits that there is not a direct, long-term correlation between a country's economic development and its citizens' happiness.

Myopia

A condition of the eyes where close objects appear clearly, but distant ones don't.

Solar City

A city or urban area that predominantly uses solar energy to meet its energy needs, often through widespread installation of solar panels.

Related Questions