You Are Concerned That Your Current Single Plantwide Allocation Rate

question 178

Essay

You are concerned that your current single plantwide allocation rate is giving inaccurate results and would like to switch to an activity-based costing method.Why is activity-based costing considered more accurate than traditional costing methods?