The Present Value of the Total Costs Over a Five

question 97

Multiple Choice

The present value of the total costs over a five year period for Project April is $50,000.The net present value of total costs over a 4 year period for Project October is $40,000.The company uses a discount rate of 9%.Which project should it choose and why?