Harvey Corporation

question 5

Multiple Choice

Answer the following questions using the information below:
Harvey Corporation manufactured 1500 chairs during June.The following variable overhead data pertain to June:
 Budgeted variable overhead cost per unit $12.00 Actual variable manufacturing overhead cost $20800 Flexible-bud get amount for variable manufacturing overhead $18000 Variable manufacturing overhead efficiency variance $360 unfavourable \begin{array}{ll}\text { Budgeted variable overhead cost per unit } & \$ 12.00 \\\text { Actual variable manufacturing overhead cost } & \$ 20800 \\\text { Flexible-bud get amount for variable manufacturing overhead } & \$ 18000 \\\text { Variable manufacturing overhead efficiency variance } & \$ 360 \text { unfavourable }\end{array}

-What is the variable overhead flexible-budget variance?


Definitions:

Split Shifts

A work schedule that divides an employee's workday into two or more segments with a break in between, typically unpaid.

Educational Achievements

The accomplishments or credentials obtained through formal schooling or training programs, such as degrees, diplomas, or certificates.

Validity Generalization

A statistical approach asserting that test validity can be generalized across various contexts, especially used in psychometrics for employment testing.

Criterion-related Validity

A measure of the effectiveness of a test or assessment in predicting an individual's performance on related tasks or outcomes.

Related Questions