Explain why there is no efficiency variance for fixed manufacturing overhead costs.


Definitions:

Expected Time

An estimation of the duration it would likely take to complete a task, often used in project management for scheduling.

PERT Times

entails the estimated durations in the Program Evaluation and Review Technique, a method used in project management.

Optimistic Time

The shortest possible time in which a task or project can be completed, assuming everything goes better than expected.

PERT Analysis

A project management tool used to schedule, organize, and coordinate tasks within a project, focusing on analyzing the time needed to complete each task.