Given the partial project network below and the fact that F can be crashed three times if xt = start
time of Activity i, and yi = amount of crash time used for Activity i.  Given the partial project network below and the fact that F can be crashed three times if x<sub>t</sub> = start time of Activity i, and y<sub>i</sub> = amount of crash time used for Activity i.    a. Which of the following is correct? x<sub>F</sub>  \ge  x<sub>D</sub> + 10 - y<sub>D</sub> or x<sub>F</sub>  \ge  x<sub>E</sub> + 10 + y<sub>E</sub> or y<sub>D</sub>, y<sub>E</sub>  \le  0 or x<sub>F</sub> -x<sub>D</sub> - x<sub>E</sub> + 10  \ge  3 b. Which of the following is correct? y<sub>D</sub>  \le  3 or y<sub>E</sub>  \le  3 or y<sub>F</sub> = y<sub>D</sub> + y<sub>E</sub> or y<sub>F </sub> \le  3
a. Which of the following is correct? xF \ge xD + 10 - yD or xF \ge xE + 10 + yE or yD, yE \le 0 or xF -xD - xE + 10 \ge 3
b. Which of the following is correct? yD \le 3 or yE \le 3 or yF = yD + yE or yF \le 3


Definitions:

Ethical Violations

Actions or behaviors that breach established codes of conduct or moral principles, often resulting in professional or legal consequences.

Experiments

are systematic investigations conducted to test hypotheses, involving controlled variables to determine effects and outcomes.

Qualitative Research

A data-collection process that examines and interprets nonnumerical material.

Field Research

A method of collecting data through first-hand observation or interaction within a natural setting outside the laboratory or office.

Related Questions