Given the Partial Project Network Below and the Fact That \ge

question 14

Essay

Given the partial project network below and the fact that F can be crashed three times if xt = start
time of Activity i, and yi = amount of crash time used for Activity i.  Given the partial project network below and the fact that F can be crashed three times if x<sub>t</sub> = start time of Activity i, and y<sub>i</sub> = amount of crash time used for Activity i.    a. Which of the following is correct? x<sub>F</sub>  \ge  x<sub>D</sub> + 10 - y<sub>D</sub> or x<sub>F</sub>  \ge  x<sub>E</sub> + 10 + y<sub>E</sub> or y<sub>D</sub>, y<sub>E</sub>  \le  0 or x<sub>F</sub> -x<sub>D</sub> - x<sub>E</sub> + 10  \ge  3 b. Which of the following is correct? y<sub>D</sub>  \le  3 or y<sub>E</sub>  \le  3 or y<sub>F</sub> = y<sub>D</sub> + y<sub>E</sub> or y<sub>F </sub> \le  3
a. Which of the following is correct? xF \ge xD + 10 - yD or xF \ge xE + 10 + yE or yD, yE \le 0 or xF -xD - xE + 10 \ge 3
b. Which of the following is correct? yD \le 3 or yE \le 3 or yF = yD + yE or yF \le 3


Definitions:

Operating Costs

Expenses associated with the day-to-day functioning of a business, such as rent, utilities, and payroll, excluding costs related to production.

Annual Cost

The total expenses associated with maintaining or operating something over the course of a year.

Useful Life

The estimated period over which a fixed asset is expected to be useful to the owning entity, crucial for calculating depreciation.

Machine

Equipment or devices designed to perform specific tasks, often used in manufacturing and production processes.