Consider the Work Sampling Information Below  Cycles (Actual Time in Seconds) \text { Cycles (Actual Time in Seconds) }

question 35

Essay

Consider the work sampling information below.  Cycles (Actual Time in Seconds) \text { Cycles (Actual Time in Seconds) }
 Work  Task 123456 Q 253027312220 R 405235424738 S 606250556258\begin{array} { | l | l | l | l | l | l | l | } \hline \begin{array} { l } \text { Work } \\\text { Task }\end{array} & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Q } & 25 & 30 & 27 & 31 & 22 & 20 \\\hline \text { R } & 40 & 52 & 35 & 42 & 47 & 38 \\\hline \text { S } & 60 & 62 & 50 & 55 & 62 & 58 \\\hline\end{array}
a. If the performance rating factor for Q = 0.80, R = 1.10, and S = 1.10 and the total allowance is 17 percent, determine the normal time for the job.
b. With the allowance of 17 percent, determine the output per hour.


Definitions:

SCM

The process of overseeing the movement of goods, information, and money from the beginning of the supply chain with suppliers, through manufacturers and wholesalers, down to retailers and finally consumers, is known as Supply Chain Management.

Pricing

The process of determining what a company will receive in exchange for its products or services.

Supplier Relationships

The interactions and partnerships between businesses and their providers of goods or services.

Pull Model

A pull model is a supply chain strategy where the production of goods is initiated by actual customer demand rather than forecasted demand.