An Assembly Line with 28 Operations Is to Be Balanced

question 30

Multiple Choice

An assembly line with 28 operations is to be balanced. The total amount of time required for all 28 operations is 39 minutes. The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes. The line will operate for 450 minutes per day.
1) Determine the minimum and maximum cycle time.
2) What is the output rate if the cycle time is set at 2.2 minutes?


Definitions:

Competing Interests

Conflicting goals or objectives among different groups or individuals, often requiring negotiation or compromise.

Small States

Political entities or regions characterized by a small geographic area or population, often possessing limited political influence on a global scale.

Large States

States with significant populations or geographical areas, often having considerable influence in national politics and elections.

Proposing Amendments

The process by which changes or additions are made to the Constitution of the United States, typically requiring approval by both Congress and the states.

Related Questions