An Assembly Line with 28 Activities Is to Be Balanced

question 28

Multiple Choice

An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 88 minutes. The longest activity is 2.2 minutes and the shortest is 0.8 minutes. The line will operate for 450 minutes per day. Using a cycle time of 60 seconds, determine an assembly-line balance by selecting the longest-processing-time task available. Compute the total idle time and assembly-line efficiency.
-The total idle time is _____ seconds.


Definitions:

Appraisal

A formal assessment process in which an employee's job performance and productivity are evaluated, typically involving feedback and discussions about development and goals.

Compensation System

A structured approach to pay and benefits that an organization offers to its employees in exchange for their work and contributions.

Customer Satisfaction Measure

Metrics or tools used to evaluate the degree to which a product or service meets or exceeds the expectations of its customers.

Staffing Efforts

The activities involved in identifying, acquiring, and managing personnel to meet an organization's needs.

Related Questions