An Electronics Company Wants to Develop an MRP Schedule for One

question 101

Essay

An electronics company wants to develop an MRP schedule for one of its key components, a specialized chip. The lot size is 600, the lead time is 2 weeks, there are 900 units on hand with 300 of those as safety stock and 500 already allocated. There are gross requirements for 2000 units in Week 3 and 1500 units in Week 5. There are 600 units scheduled to be received in Week 1.
a.What is the number of units available in Week 3?
b.What is the planned order receipt for Week 5?


Definitions:

Expectant Father

A man whose partner is pregnant, awaiting the birth of their child.

Developmental Tasks

Specific achievements or milestones that people are expected to accomplish at different stages of their lives.

Couple's Relationship

The romantic and emotional bond between two individuals in a committed partnership, which includes mutual affection and support.

Pregnancy

The condition or period of being pregnant, where a fetus develops inside a woman's uterus.

Related Questions