Examlex

Solved

The Following Five Jobs, Along with Their Processing Time and Due

question 50

Multiple Choice

The following five jobs, along with their processing time and due dates, are given below.
 Processing  Days Due  Job  Time (days)   From Today  A 812 B 49 C 36 D 77 E 520\begin{array}{|l|l|l|}\hline & \text { Processing } & \text { Days Due } \\\hline \underline{\text { Job }} & \underline{\text { Time (days) }} & \text { From Today } \\\hline \text { A } & 8 & 12 \\\hline \text { B } & 4 & 9 \\\hline \text { C } & 3 & 6 \\\hline \text { D } & 7 & 7 \\\hline \text { E } & 5 & 20 \\\hline\end{array}

-Using the shortest processing time (SPT) rule, the average flow time for the five jobs is _____.


Definitions:

Related Questions