Consider the following project network. Time estimates are in weeks.  Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | }  \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}  -In the previous project network, the critical path activities are: A)  A,B, and C. B)  A,B,C,D, and F. C)  A,B,D, and F. D)  B,C,D, and F. Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}
-In the previous project network, the critical path activities are:


Definitions:

Selective Attention

The cognitive process of focusing on particular objects or tasks in the environment while ignoring others, enabling the prioritization of information processing.

Perceptual Errors

Mistakes in judgment or interpretation made by individuals due to subjective biases, misleading appearances, or incorrect information.

Perception Influences

Factors that affect how individuals interpret and make sense of their sensory experiences.

Recognizing

The act of identifying or acknowledging the existence or truth of something.

Related Questions