You Are Responsible for Managing an Advertising Project with the Following

question 83

Multiple Choice

You are responsible for managing an advertising project with the following activities (times are given in weeks) .
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)   (Weeks)   Cost ($)  Cost ($)  A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$) \\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES
-What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?


Definitions:

U.S. and Foreign Country

A diplomatic, economic, or cultural relationship between the United States and another sovereign nation.

Stare Decisis

A legal principle that dictates courts should follow the precedent set by previous decisions when resolving similar cases to ensure consistency and predictability in the law.

American Legal System

The legal framework consisting of both federal and state laws, including statutes, regulations, and court decisions.

Business Managers

Individuals responsible for overseeing and directing the operations of a business to achieve its goals.

Related Questions