You are responsible for managing a project with the following activities (times are given in weeks) :
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)   (Weeks)   Cost ($)  Cost ($)  A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$) \\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}
-What is the total project (normal plus crash) cost?


Definitions:

Experiment

A scientific procedure undertaken to make a discovery, test a hypothesis, or demonstrate a known fact by controlling and varying one or more variables.

Mutually Exclusive

Events that cannot occur at the same time, implying that the occurrence of one event excludes the occurrence of the other.

Events

Outcomes or occurrences that can be clearly defined, measured, and distinguished from other events in a probability context.

Outcomes

The possible results or consequences of an experiment, procedure, or situation.

Related Questions