Data Regarding the Activities for a Project Are Presented Below

question 56

Essay

Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A-D-H-I-J-K.  Activity  Optimistic Time  Most Likely Time  Pessimistic Time  A 7914 B 228 C 81216 D 3510 E 468F6810G234H228I6816J4614K225\begin{array}{|c|c|c|c|}\hline\text { Activity } & \text { Optimistic Time } & \text { Most Likely Time } & \text { Pessimistic Time } \\\hline \text { A } & 7 & 9 & 14 \\\hline \text { B } & 2 & 2 & 8 \\\hline \text { C } & 8 & 12 & 16 \\\hline \text { D } & 3 & 5 & 10 \\\hline \text { E } & 4 & 6 & 8 \\\hline \mathrm{F} & 6 & 8 & 10 \\\hline \mathrm{G} & 2 & 3 & 4 \\\hline \mathrm{H} & 2 & 2 & 8 \\\hline \mathrm{I} & 6 & 8 & 16 \\\hline \mathrm{J} & 4 & 6 & 14 \\\hline \mathrm{K} & 2 & 2 & 5 \\\hline\end{array}
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?


Definitions:

Analytical Intelligence

One aspect of intelligence that involves the ability to analyze, evaluate, judge, compare, and contrast.

Practical Intelligence

An aspect of intelligence related to the application of knowledge and skills in solving everyday problems and achieving goals.

Cultural Differences

Variations in the practices, customs, and social norms among different societies and ethnic groups.

IQ

Short for Intelligence Quotient, a measure of a person's cognitive abilities in relation to their age group.

Related Questions