question 50

Multiple Choice

Robin Construction Company began a long-term contract in 2012.The contract price was $600,000.The estimated cost of the contract at the time it was begun was $450,000.The actual cost incurred in 2012 was $300,000.The contract was completed in 2013 and the cost incurred that year was $180,000.Under the percentage of completion method: