Examlex

Solved

Sanchez Company Planned to Produce 12,000 Units

question 39

Multiple Choice

Sanchez Company planned to produce 12,000 units.This level of activity required 20 setups at a cost of $22,000 plus $500 per setup.Actual production was 10,000 units,requiring 15 setups.Actual setup cost was $26,000.At 10,000 units,what is the flexible budget amount for total setup costs?