Some Level of Risk Planning Should Be Done During ____

question 15

Multiple Choice

Some level of risk planning should be done during ____ of the project life cycle to make sure that a contractor understands the risks involved with bidding on a proposed project.With knowledge of potential risks, the contractor can include contingency or management reserve amounts in the bid price.