An assembly line with 28 activities is to be balanced.The total amount of time required for all 28 activities is 39 minutes.The longest activity is 2.2 minutes and the shortest is 0.8 minutes.The line will operate for 450 minutes per day.Using a cycle time of 60 seconds, determine an assembly line balance by selecting the longest task available.Compute the total idle time, and assembly line efficiency.
Intra-entity Gross Profit
This refers to the gross profit earned by a company from sales made internally between its own divisions or subsidiary entities.
Cost of Goods Sold
The direct costs attributable to the production of the goods sold by a business, including materials and labor costs.
Equity Method
An accounting technique used to record investments in other companies, where the investment is initially recorded at cost and subsequently adjusted for the investor's share of the investee's profit or loss and dividends received.
Intra-entity Gross Profit
Profits resulting from transactions within the same entity, often requiring adjustment during the consolidation process for accurate financial reporting.
Q1: Marketing an operations generally prefer high inventory
Q24: An electronics company wants to develop an
Q34: Contrast the two views of a value
Q37: Safety capacity or a capacity cushion is<br>A)Needed
Q50: A computer manufacturer currently has a 15
Q50: What is the difference between corporate, business
Q54: Design flexibility is the ability to respond
Q55: Explain the difference between statistical forecasting and
Q61: Measuring and reporting performance results can be
Q84: What is inventory management and why is