A Company Has a PERT Project with Path B-D-E-G-I That

question 24

Essay

A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:
A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:    a.What is the expected duration for activity  e ? b.What is the variance for activity  b ? c.What is the standard deviation of the path?
a.What is the expected duration for activity "e"?
b.What is the variance for activity "b"?
c.What is the standard deviation of the path?


Definitions:

Contractual Relationship

A legal bond formed between parties through a contract, entailing mutual rights and obligations.

Partnership Registration

The process of legally declaring a partnership to ensure it's recognized by law and able to conduct business.

Limited Liability

A legal structure where a person's financial responsibility is bounded to the amount invested in a business, protecting personal assets from company debts.

Professional Duties

Obligations that individuals in certain professions must follow based on standards of their profession and ethical guidelines.

Related Questions