The manager at a sewing factory uses a piece rate pay system.She has just received an order for 600 dresses from the discount house downtown.She is trying to figure out what her costs are for the project.She has conducted a time study and found operations take this long:
2 minutes to sew one sleeve
3 minutes to sew body of the dress
3.5 minutes to hem all unfinished edges
1 minute to attach the collar
3 minutes to attach all buttons
The workers must sit idle while they wait for supplies on the conveyor belt for an average of 30 seconds.Their performance rating is equal to one.She pays the workers $6.00 per hour.
a.What is the allowance factor for the operation?
b.What is the labor standard (in minutes) per dress?
c.What is the labor cost per dress?
d.What is the labor cost for the entire order of 600 dresses?
Digital Content
Any content that exists in the form of digital data, including text, images, audio, and video files.
Voice Synthesizer
A software or hardware that generates spoken words from text, often used in communication devices and digital assistants.
Battery Charge
The process of replenishing a battery's power or the current state of its power level.
Architectural Blueprints
Detailed drawings and specifications used in the planning, design, and construction of buildings and structures.
Q1: Unavoidable delays should not be included in
Q8: A major advantage of offshore production is
Q14: When the currency of an exporter is
Q21: A simulator is a general purpose simulation
Q24: A major difference between U.S. segment disclosures
Q40: Differentiate between a feasible solution and an
Q42: Which lot sizing rule is best when
Q50: Toyota classified waste into seven major categories.Those
Q58: When producing a broad goods or service
Q63: Synchronization of the value chain is a