What is the correct constraint for node 2 in the following diagram? What is the correct constraint for node 2 in the following diagram?   A) X<sub>12 </sub>+ X<sub>23 </sub>= 100 B) X<sub>12 </sub>− X<sub>23 </sub>≤ 100 C) −X<sub>12 </sub>+ X<sub>23 </sub>≥ −100 D) X<sub>12 </sub>− X<sub>23 </sub>≥ 100