A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.The following spreadsheet was developed to determine the earliest start times and latest start times for the project.Based on the data in the spreadsheet,which activities are on the critical path?
ABCDEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 1010103 B  Activity B  A 4151504 C  Activity C  B 3585805 D  Activity D  C 381181106 E  Activity EB2575707 F Activity F E471171108 G  Activity G  D, F 2111311130\begin{array}{|r|r|r|r|r|r|r|r|r|r|}\hline&A&B&C&D&E&F&G&H&I\\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } &\text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 1 & 0 & 1 & 0 & 1 &0\\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 4 & 1 & 5 & 1 & 5 &0 \\\hline 4 & \text { C } & \text { Activity C } & \text { B } & 3 & 5 & 8 & 5 & 8 &0\\\hline 5 & \text { D } & \text { Activity D } & \text { C } & 3 & 8 & 11 & 8 & 11 &0 \\\hline 6 & \text { E } & \text { Activity } \mathrm{E} & \mathrm{B} & 2 & 5 & 7 & 5 & 7 &0\\\hline 7 & \mathrm{~F} & \text { Activity F } & \mathrm{E} & 4 & 7 & 11 & 7 & 11 &0 \\\hline 8 & \text { G } & \text { Activity G } & \text { D, F } & 2 & 11 & 13 & 11 & 13&0 \\\hline\end{array}


Definitions:

Franchisee

The purchaser of a franchise.

Personal Assets

Items of value owned by an individual, including tangible assets like real estate and vehicles, and intangible assets like investments and bank accounts.

Related Questions