A company made the following expenditures in connection with the construction of its
new building:
Architect’s fees for the new building Cash paid for land and run-down building on the land Removal of old building Salvage from sale of old building materials Construction survey to site the new building Legal fees for title search Excavation for basement construction Machinery purchased for operations Storage charges on machinery because building was not ready when machinery was delivered Freight on machinery purchased Hauling charges to deliver machinery from storageto new building Construction costs of new building Landscaping Installation of machinery $12,000300,00018,0004,0001,5003,00025,000100,0009001,6003001,000,00020,0002,500
Prepare a schedule showing the amounts to be recorded as land,buildings,and machinery.
Definitions:
Option Group
A user interface control that presents a set of mutually exclusive choices to the user, often represented as radio buttons or a dropdown list.
Command Button
A control element in graphical user interfaces that executes a specific command or action when clicked by the user.
Linked Data
A set of best practices for connecting structured data across the web, enabling data from different sources to be connected and queried.
Combo Box Wizard
A tool in software applications that guides users through the steps of creating a combo box, which combines a text box with a list box.