Use the Values in the Table to Calculate Activity Durations

question 100

Essay

Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
 Activity  Predecessor  Optimistic  Likely  Pessimistic  A 4610 B  A 258 D  A 679 E  B 3920 F  C 7911\begin{array} { | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Likely } & \text { Pessimistic } \\\hline \text { A } & - & 4 & 6 & 10 \\\hline \text { B } & \text { A } & 2 & 5 & 8 \\\hline \text { D } & \text { A } & 6 & 7 & 9 \\\hline \text { E } & \text { B } & 3 & 9 & 20 \\\hline \text { F } & \text { C } & 7 & 9 & 11 \\\hline\end{array}


Definitions:

Bonds Payable

Bonds payable refers to the amount of money a company owes to holders of its bonds, representing a long-term debt obligation.

Credit Cash

An accounting entry that represents an increase in cash or cash equivalents, indicating funds being added to the company’s assets.

Bond Interest Expense

The cost incurred by an issuer of bonds for the interest required to be paid to bondholders.

Contract Rate

The agreed-upon rate of interest or payment terms specified within a financial contract or agreement.

Related Questions