What Is the Late Finish Time for Activity D Given

question 16

Multiple Choice

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5 B 7 D 8 A  D 7 A  E 4 B  F 8 C, D  G 9 E, F  H 7 G \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & - \\\hline \text { B } & 7 & - \\\hline \text { D } & 8 & \text { A } \\\hline \text { D } & 7 & \text { A } \\\hline \text { E } & 4 & \text { B } \\\hline \text { F } & 8 & \text { C, D } \\\hline \text { G } & 9 & \text { E, F } \\\hline \text { H } & 7 & \text { G } \\\hline\end{array}


Definitions:

Pension Plan

A retirement plan funded by an employer, offering income to employees after they retire.

Product Warranty Expense

The cost associated with the obligation of a company to repair or replace defective products sold to customers, recognized as a liability.

Social Security Tax Rate

The Social Security tax rate is a percentage of income that is taxed to fund the Social Security program, paid by both employees and employers.

Medicare Tax Rate

The percentage of an employee's earnings that is withheld by the employer to contribute to the U.S. Medicare program, which provides health insurance to eligible individuals.

Related Questions