Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor  A 8 B 4 A  C 5 B, F  D 12 A E8 D  F 4 D G9 E, F \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 8 & \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 5 & \text { B, F } \\\hline \text { D } & 12 & \text { A } \\\hline E & 8 & \text { D } \\\hline \text { F } & 4 & \text { D } \\\hline G & 9 & \text { E, F } \\\hline\end{array}


Definitions:

Capacity Decisions

Capacity decisions are strategic choices made by businesses regarding the amount of production resources available to meet demand, including facilities, equipment, and labor force.

Maximize Profit

The process of making business decisions that increase the difference between total revenue and total costs to the highest possible level.

Constant Output Rate

A production strategy where goods or services are produced at a uniform rate, maintaining a steady level of output over time.

Demand Manipulation

Techniques used by businesses to influence customer demand, either by stimulating interest in products or by adjusting supply levels.

Related Questions