A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days?
Stakeholders
Individuals or groups with an interest in a company's operations and outcomes, including employees, customers, investors, suppliers, and the community.
Environmental Risks
Potential threats and uncertainties to the environment resulting from human activities or natural processes that may cause harm to living organisms and ecosystems.
Consumer Perceptions
Consumer perceptions are the attitudes, beliefs, and impressions that consumers have towards a product, brand, or service, influencing their purchasing decisions.
Relationship and Image Costs
Relationship and Image Costs entail the expenses associated with building and maintaining relationships with stakeholders and the cost of developing and preserving a company's public image.
Q11: A project that is terminated by extinction
Q36: What is the early start time
Q39: The BOT option for large projects is
Q48: The legal department is needed to review
Q49: Systems for monitoring the project's scope,schedule,and costs
Q58: A project consists of six activities
Q65: Which statement about scope management is BEST?<br>A)
Q74: What is configuration management and why is
Q76: Which step in project management requires project
Q79: These can be located by doing a