Examlex

Solved

A Project Has the Precedence Requirements and Activity Durations Shown

question 13

Multiple Choice

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project?  Time  Predecessor A7B8 AC13 AD8 AE7 BF6CG6DH11EI12GT14H,F,I\begin{array} { | l | l | l | } \hline & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline \mathrm { B } & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~A} \\\hline \mathrm { D } & 8 & \mathrm {~A} \\\hline \mathrm { E } & 7 & \mathrm {~B} \\\hline \mathrm { F } & 6 & \mathrm { C } \\\hline \mathrm { G } & 6 & \mathrm { D } \\\hline \mathrm { H } & 11 & \mathrm { E } \\\hline \mathrm { I } & 12 & \mathrm { G } \\\hline \mathrm { T } & 14 & \mathrm { H } , \mathrm { F } , \mathrm { I } \\\hline\end{array}


Definitions:

Related Questions