-What Is the Earliest That Activity D Can Begin If

question 46

Multiple Choice

  -What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? A)  Day 15 B)  Day 7 C)  Day 5 D)  Day 3
-What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?